Indexes of building and assembly works

INDEXES of changes of building and assembly works cost for calculation at building of objects according to the design estimates  worked out without application of recourse estimate norms in the basic prices of 1991 (for the works which are not relieved from the tax to the added cost)


Name 

Regions                             


Minsk city

Brest

Vitebsk

Gomel

Grodno

Minsk

Mogilev

1. Indexes on expenditure elements:

1.1 Wage          

1692,673

1692,673

1692,673

1692,673 

1692,673

1692,673 

1692,673

1.2 Transport cost        

3226,557

3118,514

3248,301

3565,685 

3308,471

3000,260 

3084,093

1.3 Overhead charges        

1737,462

1739,183

1731,785

1745,689 

1735,316

1734,319 

1730,532

1.4 Planned accumulations     

741,232

818,162

681,075 

586,923 

781,353

644,459 

631,603

1.5 Temporary buildings and constructions     


3221,184


3209,186


3224,386


3335,761 


3288,524


3172,918 


3151,558

1.6 Winter rise in price

2752,670

2720,166

2703,748

2854,892 

2792,004

2713,912 

2690,488

2. Indexes (reference data):                                

The general index  of changes  of cost on building and assembly works with the account of material resources cost, including




2298,906




2294,116




2251,183




2322,936 




2351,808




2245,665 




2257,065

- building materials,    
workpieces  and constructions    


3669,077


3660,505


3766,081


3728,950 


3750,069


3663,003 


3651,692

- machines and mechanisms exploitation


3091,116


3139,717


2692,040


3637,041 


3127,437


3047,381 


3144,722

Coefficient to the tariff on automobile transportation


3172,922


3049,624


3252,565


3740,622 


3343,541


2852,880 


3016,676